Component | % Weightage as per Schedule – G | Physical Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
Road Works i/c Culverts, Minor Bridges, Underpasses & Approaches | 64.45% | 1.31% | 63.32% |
Major Bridge Works & ROB / RUB | 3.14% | 0.07% | 3.04% |
Structures [ Elevated Section | Reinforced Earth] | 7.52% | 0.00% | 7.52% |
Other Works | 24.89% | 1.83% | 20.74% |
Total | 100.00% | 3.22% | 94.64% |