Project Milestone |
Description (Days from Appointed Date ) |
Planned | Actual | Delay (No. of months) | Current Physical Status |
||
---|---|---|---|---|---|---|---|
Physical Status Progress (%) |
Scheduled Date | Physical Progress (%) |
Achieved Date | ||||
Project Milestone-I | 200 | 20% | 06-09-2021 | 22-11-2021 | - | ||
Project Milestone-II | 450 | 35% | 14-05-2022 | 10-04-2022 | - | ||
Project Milestone-III | 600 | 75% | 11-10-2022 | 28-10-2022 | |||
Schedule Completion Date | 910 | 100% | 17-08-2023 | 94.64% | |||