banner

Project Milestones

Project Milestones

Project
Milestone
Description
(Days from
Appointed
Date )
Planned Actual Delay (No. of months) Current
Physical Status
Physical Status
Progress (%)
Scheduled Date Physical
Progress (%)
Achieved Date
Project Milestone-I20020%06-09-202122-11-2021-
Project Milestone-II45035%14-05-202210-04-2022-
Project Milestone-III60075%11-10-202228-10-2022
Schedule Completion Date910100%17-08-202394.64%