BRIEF of HIGHWAY PROGRESS in GENERAL (from Km 302+108 to 373+085)

Sr. No.

Description

Scope of Work Km. (4 Lane)

Work Complete Km. (4 Lane)

Remarks

1Clearing & Grubbing139.59137.58
2Sub-Grade139.59 133.06
3GSB139.59 131.88
4DLC135.996 127.86
5PQC139.59 122.19
6Subgrade (SR) 53.321 42.99
7GSB/CTSB(SR) 53.321 41.96
8WMM(SR) 53.321 29.18
9DBM(SR) 53.321 37.50
10BC(SR) 53.321 21.31